BIF Act QLD  Online Claim Form

QLD: before you submit

  • You need a construction contract (written or verbal) for work in Queensland.
  • Claims are made on each reference date (usually the last day of the month), one per reference date, within 6 months of when you last did the work. Final claims have their own time limits.
  • The claim must identify the work, state the amount and request payment. A document headed “invoice” requests payment.
  • The respondent has 15 business days to give a payment schedule.
  • No schedule and not paid? There is no notice step in Queensland: you can apply for adjudication directly, within 30 business days.

Need help? See our QLD Security of Payment Act page, or call or contact us.