BIF Act QLD Online Claim Form
QLD: before you submit
- You need a construction contract (written or verbal) for work in Queensland.
- Claims are made on each reference date (usually the last day of the month), one per reference date, within 6 months of when you last did the work. Final claims have their own time limits.
- The claim must identify the work, state the amount and request payment. A document headed “invoice” requests payment.
- The respondent has 15 business days to give a payment schedule.
- No schedule and not paid? There is no notice step in Queensland: you can apply for adjudication directly, within 30 business days.
Need help? See our QLD Security of Payment Act page, or call or contact us.