NSW: before you submit

  • You need a construction contract (written or verbal) for work in NSW.
  • Claims can be served from the last day of each month you worked, one per month, within 12 months of when you last did the work.
  • The claim must state that it’s made under the Building and Construction Industry Security of Payment Act 1999. Head contractors must attach a supporting statement.
  • The respondent has 10 business days to give a payment schedule.
  • No schedule and not paid by the due date? You must serve a notice within 20 business days before applying for adjudication.