Security Of Payments Act VIC Online Claim Form

VIC: before you submit

  • You need a construction contract (written or verbal) for work in Victoria.
  • Claims can be served from the last day of each month you worked, one per month, up to 6 months after practical completion of all the work (or later if your contract allows).
  • The claim must state that it’s made under the Building and Construction Industry Security of Payment Act 2002, and be in the prescribed form if one applies.
  • The respondent has 10 business days to give a payment schedule.
  • No schedule and not paid by the due date? You must serve a notice within 10 business days before applying for adjudication.

Need help? See our VIC Security of Payment Act page, or call or contact us.