NT Security of Payment Act Flowchart
How a payment claim moves through the Northern Territory security of payment process, from making your claim to enforcing an adjudication decision. Find the step you’re at and check your deadlines.
Make your payment claim
- Claim when your contract allows. If the contract says nothing, you can claim any time after you have carried out some of the work.
- The claim must be in writing, addressed to the other party, dated, state your name and the amount, and itemise the work in enough detail for them to assess it.
- Applies to construction contracts for work on a site in the Northern Territory entered into from 1 July 2005. Either party (contractor or principal) can make a payment claim.
They must respond or pay
Under your contract's terms. If the contract says nothing, they must either give you a written notice of dispute within 10 working days (and pay any undisputed part), or pay the whole claim within 20 working days. Any contract term allowing more than 30 working days to pay is read down to 30.
A payment dispute arises when
- your claim is rejected or wholly or partly disputed, or
- the amount claimed is not paid in full by the due date, or
- retention money or security is not paid or returned when it is due.
Apply for adjudication
- Within 65 working days after the payment dispute arises. There is no notice step first.
- Prepare a written application with the contract (or relevant parts), the payment claim and all your supporting documents and submissions.
- Serve it on the other party and on the adjudicator named in your contract (if they agree), the appointer named in your contract, or otherwise a prescribed appointer you choose. Pay any deposit required.
The adjudicator decides
- The appointer appoints a registered adjudicator within 5 working days.
- The other party responds within 15 working days of being served with your application.
- The adjudicator decides within 10 working days after the response (or after the response was due). They can add 5 working days for fairness, or more with the Registrar's consent.
- If no decision is made in time, the application is taken to be dismissed. You can apply again within 20 working days. Some dismissals can be reviewed by NTCAT.
They must pay by the date in the decision
The adjudicator sets the date for payment. Interest runs on any amount unpaid after that date.
Not paid? Enforce it as a court order
- Get a copy of the determination certified by the Construction Contracts Registrar.
- File it in a court with an affidavit stating the amount unpaid. It is then taken to be an order of that court and can be enforced.
- You can also suspend work on at least 3 working days written notice until you are paid.
Simplified guide to the Construction Contracts (Security of Payments) Act 2004 (NT), as in force at 25 May 2024. Working days exclude weekends, public holidays and 25 December to 7 January. Mining, oil and gas drilling and watercraft are excluded, and high value contracts may use their own dispute process. Your contract can change some of these steps. General information only, not legal advice. Last reviewed October 2026.
Not sure where you're up to? Call 1300 732 687 or contact us and we'll tell you your deadlines.