TAS Security of Payment Act
Get paid for your building and construction work in Tasmania
The Building and Construction Industry Security of Payment Act 2009 (Tas) gives anyone who carries out building or construction work, or supplies related goods and services, a legal right to progress payments. It also gives you a fast, low-cost way to recover what you’re owed.
SECURITY OF PAYMENT Services prepares and serves payment claims and adjudication applications for contractors, subcontractors and suppliers across Tasmania, with a 98% success rate.
Who the Act covers
The Act covers building and construction contracts for work in Tasmania, whether written or verbal. That includes head contractors, subcontractors, suppliers and consultants. Unlike most states, Tasmania’s Act also covers residential work for home owners.
Key time frames
- Reference dates: you can claim on the date your contract sets. If it doesn’t set one, you can claim on the last day of each month in which you work. You can serve one payment claim for each reference date.
- Time limit: a claim must be served within 12 months after the work was last carried out, or within any longer period your contract allows.
- Payment schedule: the respondent has 10 business days after receiving your claim to provide a payment schedule, or less if the contract says so. If the claim is against a home owner who isn’t a building practitioner, they have 20 business days. If they don’t respond in time, they become liable for the full amount claimed.
- Due date: payment is due when the contract says. If the contract is silent, it’s due within the same 10 or 20 business days. Interest runs on late payments.
Applying for adjudication
You can apply if:
- the payment schedule offers less than you claimed — apply within 10 business days after you receive it;
- the respondent doesn’t pay the scheduled amount — apply within 20 business days after the due date; or
- no payment schedule is given and the claim isn’t paid — first notify the respondent within 20 business days after the due date that you intend to apply. They then have 5 business days to provide a schedule, and you apply within the 10 business days after that.
A copy of the application must be served on the respondent. A respondent who didn’t provide a payment schedule can’t put a defence at adjudication.
A winning application depends on getting the timing right, choosing the right nominating authority, and putting together a strong written submission backed by solid evidence. We prepare, lodge and serve the whole application for you.
After the determination
If the adjudicated amount isn’t paid, you can get an adjudication certificate and file it in court as a judgment debt, then enforce it. We handle every step from claim to enforcement and debt collection.
Debt recovery in Tasmania
If the debt has to go to court, the Magistrates Court hears claims up to $50,000. Larger claims go to the Supreme Court.
Useful links
- TAS Security of Payment flowchart
- TAS payment claim form
- Our fees
- TAS legislation: Building and Construction Industry Security of Payment Act 2009
Need help?
Call or contact us and we’ll walk you through your options.
This page is general information, not legal advice. Timeframes depend on your contract. Last reviewed October 2026.