Security Of Payments Act NT Online Claim Form

NT: before you submit

  • You need a construction contract (written, oral or a mix) for work on a site in the Northern Territory, entered into on or after 1 July 2005.
  • You can claim as your contract allows or, if it says nothing, any time after you’ve carried out some of the work.
  • If the contract says nothing, the respondent has 10 working days to give a notice of dispute, or must pay in full within 20 working days. Payment terms longer than 30 working days after the claim are read down.
  • There is no payment schedule or notice step. Your right to adjudicate starts when a payment dispute arises: your claim is rejected or disputed, isn’t paid in full by the due date, or retention money isn’t returned on time.
  • You must apply for adjudication within 65 working days after the payment dispute arises.

See the NT Security of Payment Act Flowchart for every step and deadline.

Need help? See our NT Security of Payment Act page, or call or contact us.